The client needed to replace their undersized waste water treatment (WWT) facility while maintaining plant production. The new WWT facility was designed to treat process water and rainwater at a combined rate of 500 gallons per minute, and then discharge the outfall to a local municipality.
Project Summary
- Finalized vendor-supplied Krofta P&ID’s for a new 500gpm outfall waste water treatment system
- Finalized vendor-supplied Krofta P&ID’s for a new 500 gpm outfall waste water treatment system
- Created and finalized 19 drawings, including 5 equipment layout drawings, 4 piping layout drawings, 7 structural building drawings, 3 electrical drawings, and a 3D model
- Provided foundation and building design to state building codes and coordinated building inspections
- Developed the building and equipment power plan, the first floor lighting plan, and an electrical single line
- Provided field construction assistance by overseeing 2 general and 6 sub-contractors
- Managed weekly progress meetings during 12 months of engineering and 8 additional months of field work
- Addressed construction safety concerns regarding contractor safety, fall protection, hot works, and crane lifts
- Managed and reviewed contractor’s daily PJHA work permits
- Managed permits for the client’s fall protection; hot work; confined space; line break; trench and excavation; crane utilization; and critical lifts